Dear Marcus,
Thank you for the issue report. In your case we would offer two options:
1. You can create a predefined BPMN Processes Structure Map which allows you to represent the structure of processes in a project. It shows packages, processes, subprocesses, and tasks from a selected scope, including call activities:
Process_Map.png
OR
2. You can create a Relation Map diagram and set all the criterion that you need yourself. For doing it please create a Relation Map diagram and set Context, Relation Criterion, Element Type and Scope like in the example:
Relation_Map.png
In Second case, such criterions were set:
criterion1.png
and
criterion2.png
In element type you can specify what kind of elements you want to see, e.g. only Processes and Call Activities.
Please give us a note if we've correctly interpret your problem and if the answer satisfy your needs.