Committing Changes

Discussions about Teamwork Server functionalities

Moderator: Moderators

Committing Changes

Postby ilan.sklar@gtri.gatech.edu » Wed Sep 20, 2017 9:00 am

I'm running into a problem where me and a coworker are constantly destroying each other's work because when we commit changes, sometimes we have not exercised the Update Project function.
Even if we do use UPDATE PROJECT, if we're working simultaneously in the same project and one commits changes before the other, the person to commit first has their work destroyed because the next person saves over it.

Are we doing something wrong? I would have thought Cameo only updates the files which one has locked for edit. If the element or diagram is never locked/unlocked for edit, then why is cameo committing changes for unedited items? This is causing us a lot of headaches as we keep trampling over each others work.

Thanks!
ilan.sklar@gtri.gatech.edu
Forum Newbie
Forum Newbie
 
Posts: 15
Posts Rating:0
Joined: Thu Feb 16, 2017 6:06 am
Full name: Elon S

Re: Committing Changes

Postby vidjur » Fri Sep 22, 2017 4:41 am

Hello,

Thank you for the issue report. Could you please clarify which version you are using?

Looking forward to hearing from you.
Best regards,
Vidas Jurkevicius
vidjur
Forum Beginner
Forum Beginner
 
Posts: 65
Posts Rating:1
Joined: Thu Jan 28, 2010 12:59 am

Re: Committing Changes

Postby ilan.sklar@gtri.gatech.edu » Fri Sep 22, 2017 6:39 am

18.5
Capture.PNG
You do not have the required permissions to view the files attached to this post.
ilan.sklar@gtri.gatech.edu
Forum Newbie
Forum Newbie
 
Posts: 15
Posts Rating:0
Joined: Thu Feb 16, 2017 6:06 am
Full name: Elon S

Re: Committing Changes

Postby vidjur » Mon Sep 25, 2017 12:45 am

Hello,

Could you please describe exactly what was destroyed? Scenario which describes how to reproduce this issue would be helpful.
Note, that Update should be required if new version exists on the server.

Looking forward to hearing from you.
Best regards,
Vidas Jurkevicius
vidjur
Forum Beginner
Forum Beginner
 
Posts: 65
Posts Rating:1
Joined: Thu Jan 28, 2010 12:59 am

Re: Committing Changes

Postby ilan.sklar@gtri.gatech.edu » Mon Sep 25, 2017 6:49 am

Lets say we have a teamwork server project which contains diagrams A, B, C.
-You and I simultaneously do a PROJECT UPDATE,
-I lock A for edit and modify A, then commit changes
-you lock B for edit and modify B, then commit changes - At this point, since you did not UPDATE PROJECT after I submitted A, you are now replacing the most current version of A (the one I updated) with an older version.
ilan.sklar@gtri.gatech.edu
Forum Newbie
Forum Newbie
 
Posts: 15
Posts Rating:0
Joined: Thu Feb 16, 2017 6:06 am
Full name: Elon S


Return to MagicDraw Teamwork Server